ITAC Assessment: OK0114
ITAC logo
ITAC Assessment: OK0114
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1984
Principal Product TISSUE PRODUCTS
NAICS
n/a
SIC 2621: Paper Mills
Sales Range $5
M
to 10
M
# of Employees 150
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 8,640
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $805,251 26,776,964
kWh
Natural Gas $424,963 124,003
MMBtu
Other Energy $1,877,784 356,456
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $209,604 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $18,760

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Other Energy Savings Administrative Changes Savings
01 2.3212: Optimize plant power factor $12,995 $27,645 $12,995
-
kWh
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $5,226 $18,444 $5,521
179,660
kWh
- - $(-295.0)
03 2.3212: Optimize plant power factor $1,583 $4,500 $1,583
24,033
kWh
- - -
04 2.2414: Use waste heat from hot flue gases to preheat $163,286 $127,500 - $163,286
-
MMBtu
- -
05 2.2511: Insulate bare equipment $25,975 $12,618 - $14,236
-
MMBtu
$11,739
-
MMBtu
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $404 $79 $404
13,189
kWh
- - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $135 $185 $135
2,345
kWh
- - -
TOTAL RECOMMENDED $209,604 $190,971 $20,638
219,227
kWh
$177,522
-
MMBtu
$11,739
-
MMBtu
$(-295.0)
TOTAL IMPLEMENTED $18,760 $46,353 $19,055
195,194
kWh
- - $(-295.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Other Energy Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs