ITAC Assessment: OK0107
ITAC logo
ITAC Assessment: OK0107
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1983
Principal Product OIL FIELD PUMPS
NAICS
n/a
SIC 3533: Oil and Gas Field Machinery and Equipment
Sales Range $1
M
to 5
M
# of Employees 60
Plant Area
n/a
Annual Production 3,000
pieces
Production Hrs. Annual 4,000
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $101,257 1,993,845
kWh
Natural Gas $12,123 3,299
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $25,944 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $25,944

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.3212: Optimize plant power factor $1,492 $5,215 $1,492
-
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $12,222 $34,425 $12,222
269,930
kWh
-
03 2.7243: Improve air circulation with destratification fans / other methods $4,270 $2,875 $2,291
72,685
kWh
$1,979
-
MMBtu
04 2.7221: Lower temperature during the winter season and vice-versa $5,147 $850 $2,429
73,564
kWh
$2,718
-
MMBtu
05 2.7226: Use computer programs to optimize hvac performance $2,813 $2,000 $2,813
85,287
kWh
-
TOTAL RECOMMENDED $25,944 $45,365 $21,247
501,466
kWh
$4,697
-
MMBtu
TOTAL IMPLEMENTED $25,944 $45,365 $21,247
501,466
kWh
$4,697
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs