ITAC Assessment: OK0094
ITAC logo
ITAC Assessment: OK0094
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1983
Principal Product RUBBER MOLDED PRODUCTS
NAICS
n/a
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 86
Plant Area
n/a
Annual Production 5,000,000
pieces
Production Hrs. Annual 3,750
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $38,400 784,291
kWh
Natural Gas $39,950 11,416
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,564 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,944

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $764 $183 $764
18,171
kWh
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $19 $45 $19
586
kWh
-
03 2.1233: Analyze flue gas for proper air/fuel ratio $988 $800 - $988
-
MMBtu
04 2.2135: Repair and eliminate steam leaks $2,438 $1,127 - $2,438
-
MMBtu
05 2.3212: Optimize plant power factor $728 $545 $728
-
kWh
-
06 2.2122: Install / repair insulation on condensate lines $263 $200 - $263
-
MMBtu
07 2.2122: Install / repair insulation on condensate lines $24 $30 - $24
-
MMBtu
08 2.2122: Install / repair insulation on condensate lines $156 $47 - $156
-
MMBtu
09 2.2122: Install / repair insulation on condensate lines $87 $51 - $87
-
MMBtu
10 2.2136: Install / repair insulation on steam lines $97 $49 - $97
-
MMBtu
TOTAL RECOMMENDED $5,564 $3,077 $1,511
18,757
kWh
$4,053
-
MMBtu
TOTAL IMPLEMENTED $2,944 $1,425 - $2,944
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs