Assessment Year | 1983 |
---|---|
Principal Product | RUBBER MOLDED PRODUCTS |
NAICS |
n/a
|
SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 86 |
Plant Area |
n/a
|
Annual Production | 5,000,000
pieces
|
Production Hrs. Annual | 3,750
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $38,400 | 784,291 |
kWh
|
$0.049 |
Natural Gas | $39,950 | 11,416 |
MMBtu
|
$3.50 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $5,564 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,944 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $764 | $183 |
$764
18,171
kWh
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $19 | $45 |
$19
586
kWh
|
- | |
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $988 | $800 | - |
$988
-
MMBtu
|
|
04 | 2.2135: Repair and eliminate steam leaks | $2,438 | $1,127 | - |
$2,438
-
MMBtu
|
|
05 | 2.3212: Optimize plant power factor | $728 | $545 |
$728
-
kWh
|
- | |
06 | 2.2122: Install / repair insulation on condensate lines | $263 | $200 | - |
$263
-
MMBtu
|
|
07 | 2.2122: Install / repair insulation on condensate lines | $24 | $30 | - |
$24
-
MMBtu
|
|
08 | 2.2122: Install / repair insulation on condensate lines | $156 | $47 | - |
$156
-
MMBtu
|
|
09 | 2.2122: Install / repair insulation on condensate lines | $87 | $51 | - |
$87
-
MMBtu
|
|
10 | 2.2136: Install / repair insulation on steam lines | $97 | $49 | - |
$97
-
MMBtu
|
|
TOTAL RECOMMENDED | $5,564 | $3,077 |
$1,511
18,757
kWh
|
$4,053
-
MMBtu
|
||
TOTAL IMPLEMENTED | $2,944 | $1,425 | - |
$2,944
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs