| Assessment Year | 1983 |
|---|---|
| Principal Product | CONCRETE BLOCK & PIPE |
| NAICS |
n/a
|
| SIC | 3271: Concrete Block and Brick |
| Sales Range | n/a |
| # of Employees | 44 |
| Plant Area |
n/a
|
| Annual Production | 2,500
ton
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $48,741 | 951,055 |
kWh
|
$0.051 |
| Natural Gas | $82,969 | 25,312 |
MMBtu
|
$3.28 |
| Other Energy | $18,018 | 2,031 |
MMBtu
|
$8.87 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $4,756 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | LPG Savings | Other Energy Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.1392: Replace purchased steam with other energy source | $2,343 | $5,600 | - |
$(-15,675.0)
-
MMBtu
|
$18,018
-
MMBtu
|
|
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $147 | $292 |
$147
2,931
kWh
|
- | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $82 | $70 |
$82
1,758
kWh
|
- | - | |
| 04 | 2.4133: Use most efficient type of electric motors | $960 | $2,170 |
$960
19,050
kWh
|
- | - | |
| 05 | 2.8114: Change rate schedules or other changes in utility service | $1,224 | $2,000 |
$1,224
-
kWh
|
- | - | |
| TOTAL RECOMMENDED | $4,756 | $10,132 |
$2,413
23,739
kWh
|
$(-15,675.0)
-
MMBtu
|
$18,018
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs