| Assessment Year | 2000 |
|---|---|
| Principal Product | Prestressed, Precast Concrete |
| NAICS |
n/a
|
| SIC | 3272: Concrete Products, Except Block and Brick |
| Sales Range | $5 M to 10M |
| # of Employees | 69 |
| Plant Area |
20,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 3,640
hrs
|
| Location (State) | Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $35,504 | 495,018 |
kWh
|
$0.072 |
| Electricity Demand | $8,464 | 1,584 |
kW-mo/yr
|
$5.34 |
| Electricity Fees | $2,621 | - |
|
- |
| Natural Gas | $51,408 | 7,942 |
MMBtu
|
$6.47 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $107,521 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $988 | $3,984 | n/a |
$631
12,896
kWh
|
$357
-
kW-mo/yr
|
- |
| 02 | 2.4314: Use synthetic lubricant | $301 | $65 | n/a |
$203
4,103
kWh
|
$98
-
kW-mo/yr
|
- |
| 03 | 3.5311: Recover and reuse waste material | $1,272 | $900 | n/a | - | - |
$1,272
-
lb
|
| 04 | 3.5222: Use sand for other purposes (eg construction fill, cover for municipal landfills) | $104,960 | $2,000 | n/a | - | - |
$104,960
-
lb
|
| TOTAL RECOMMENDED | $107,521 | $6,949 |
$834
16,999
kWh
|
$455
-
kW-mo/yr
|
$106,232
-
lb
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs