ITAC Assessment: OD0160
ITAC logo
ITAC Assessment: OD0160
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Prestressed, Precast Concrete
NAICS
n/a
SIC 3272: Concrete Products, Except Block and Brick
Sales Range $5
M
to 10
M
# of Employees 69
Plant Area 20,000
ft2
Annual Production 0
units
Production Hrs. Annual 3,640
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $35,504 495,018
kWh
Electricity Demand $8,464 1,584
kW-mo/yr
Electricity Fees $2,621 -
Natural Gas $51,408 7,942
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $107,521 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $988 $3,984 n/a $631
12,896
kWh
$357
-
kW-mo/yr
-
02 2.4314: Use synthetic lubricant $301 $65 n/a $203
4,103
kWh
$98
-
kW-mo/yr
-
03 3.5311: Recover and reuse waste material $1,272 $900 n/a - - $1,272
-
lb
04 3.5222: Use sand for other purposes (eg construction fill, cover for municipal landfills) $104,960 $2,000 n/a - - $104,960
-
lb
TOTAL RECOMMENDED $107,521 $6,949 $834
16,999
kWh
$455
-
kW-mo/yr
$106,232
-
lb
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs