Assessment Year | 2000 |
---|---|
Principal Product | Prestressed, Precast Concrete |
NAICS |
n/a
|
SIC | 3272: Concrete Products, Except Block and Brick |
Sales Range | $5 M to 10M |
# of Employees | 69 |
Plant Area |
20,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 3,640
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $35,504 | 495,018 |
kWh
|
$0.072 |
Electricity Demand | $8,464 | 1,584 |
kW-mo/yr
|
$5.34 |
Electricity Fees | $2,621 | - |
|
- |
Natural Gas | $51,408 | 7,942 |
MMBtu
|
$6.47 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $107,521 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $988 | $3,984 | n/a |
$631
12,896
kWh
|
$357
-
kW-mo/yr
|
- |
02 | 2.4314: Use synthetic lubricant | $301 | $65 | n/a |
$203
4,103
kWh
|
$98
-
kW-mo/yr
|
- |
03 | 3.5311: Recover and reuse waste material | $1,272 | $900 | n/a | - | - |
$1,272
-
lb
|
04 | 3.5222: Use sand for other purposes (eg construction fill, cover for municipal landfills) | $104,960 | $2,000 | n/a | - | - |
$104,960
-
lb
|
TOTAL RECOMMENDED | $107,521 | $6,949 |
$834
16,999
kWh
|
$455
-
kW-mo/yr
|
$106,232
-
lb
|
||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs