ITAC Assessment: OD0148
ITAC logo
ITAC Assessment: OD0148
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Gravure Printing
NAICS
n/a
SIC 2754: Commercial Printing, Gravure
Sales Range $10
M
to 50
M
# of Employees 175
Plant Area 180,000
ft2
Annual Production 0
units
Production Hrs. Annual 6,656
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $88,319 6,056,565
kWh
Electricity Demand $201,335 13,770
kW-mo/yr
Electricity Fees $3,406 -
Natural Gas $190,668 36,348
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $21,852 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $9,808 $43,334 $3,389
232,122
kWh
$6,419
-
kW-mo/yr
- -
02 2.1233: Analyze flue gas for proper air/fuel ratio $1,160 $1,495 - - $1,160
-
MMBtu
-
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $446 $308 $173
12,016
kWh
$273
-
kW-mo/yr
- -
04 2.7314: Reduce ventilation air $1,954 $504 $1,954
133,939
kWh
- - -
05 2.7224: Reduce space conditioning during non-working hours $4,090 $450 - - $4,090
-
MMBtu
-
06 2.7224: Reduce space conditioning during non-working hours $368 $90 $31
2,052
kWh
- $337
-
MMBtu
-
07 3.4155: Meter waste water $4,026 $4,595 - - - $4,026
-
Tgal
TOTAL RECOMMENDED $21,852 $50,776 $5,547
380,129
kWh
$6,692
-
kW-mo/yr
$5,587
-
MMBtu
$4,026
-
Tgal
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs