Assessment Year | 1999 |
---|---|
Principal Product | Carpet and Automobile Padding |
NAICS |
n/a
|
SIC | 2299: Textile goods, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 80 |
Plant Area |
50,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $64,435 | 1,634,525 |
kWh
|
$0.039 |
Electricity Demand | $39,031 | 6,887 |
kW-mo/yr
|
$5.67 |
Electricity Fees | $16,138 | - |
|
- |
Natural Gas | $26,166 | 3,157 |
MMBtu
|
$8.29 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $32,313 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,813 | $45,982 |
$9,727
247,069
kWh
|
$2,086
-
kW-mo/yr
|
- | - | - | |
02 | 2.7124: Make a practice of turning off lights when not needed | $2,361 | $1,100 |
$2,361
59,789
kWh
|
- | - | - | - | |
03 | 2.4113: Install motor voltage controller on lightly loaded motors | $858 | $4,020 |
$538
13,775
kWh
|
$320
-
kW-mo/yr
|
- | - | - | |
04 | 2.7224: Reduce space conditioning during non-working hours | $1,382 | $400 |
$255
6,448
kWh
|
- |
$1,127
-
MMBtu
|
- | - | |
05 | 3.6125: Sell combustible waste | $15,574 | - | - | - | - |
$15,574
-
lb
|
- | |
06 | 4.821: Pay bills on time to avoid late fees | $325 | - | - | - | - | - | $325 | |
TOTAL RECOMMENDED | $32,313 | $51,502 |
$12,881
327,081
kWh
|
$2,406
-
kW-mo/yr
|
$1,127
-
MMBtu
|
$15,574
-
lb
|
$325 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs