Assessment Year | 1999 |
---|---|
Principal Product | General Sawmill |
NAICS |
n/a
|
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $1 M to 5M |
# of Employees | 30 |
Plant Area |
30,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 2,295
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $69,616 | 1,126,026 |
kWh
|
$0.062 |
Electricity Demand | $16,444 | 6,839 |
kW-mo/yr
|
$2.40 |
Electricity Fees | $3,081 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $10,977 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,937 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $232 | $862 |
$189
2,931
kWh
|
$43
-
kW-mo/yr
|
- | |
02 | 2.7122: Disconnect ballasts | $1,083 | $8,452 |
$573
9,379
kWh
|
$510
-
kW-mo/yr
|
- | |
03 | 2.7135: Install occupancy sensors | $784 | $1,027 |
$784
12,603
kWh
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $622 | $800 |
$622
9,965
kWh
|
- | - | |
05 | 2.7224: Reduce space conditioning during non-working hours | $1,069 | $1,870 |
$886
14,361
kWh
|
$183
-
kW-mo/yr
|
- | |
06 | 2.4113: Install motor voltage controller on lightly loaded motors | $7,187 | $2,200 | - | - | $7,187 | |
TOTAL RECOMMENDED | $10,977 | $15,211 |
$3,054
49,239
kWh
|
$736
-
kW-mo/yr
|
$7,187 | ||
TOTAL IMPLEMENTED | $1,937 | $10,114 |
$1,384
22,275
kWh
|
$553
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs