ITAC Assessment: OD0133
ITAC logo
ITAC Assessment: OD0133
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Reconstituted Tobacco
NAICS
n/a
SIC 2141: Tobacco Stemming and Redrying
Sales Range $5
M
to 10
M
# of Employees 160
Plant Area 314,000
ft2
Annual Production 0
units
Production Hrs. Annual 8,400
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $512,071 34,601,114
kWh
Electricity Demand $806,520 59,513
kW-mo/yr
Electricity Fees $(-46,382.0) -
Natural Gas $161,354 54,107
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $44,863 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,321

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,321 $2,500 $4,321
117,526
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $33,448 $99,497 $15,271
1,032,239
kWh
$18,177
-
kW-mo/yr
03 2.3212: Optimize plant power factor $7,094 $11,100 $3,262
220,399
kWh
$3,832
-
kW-mo/yr
TOTAL RECOMMENDED $44,863 $113,097 $22,854
1,370,164
kWh
$22,009
-
kW-mo/yr
TOTAL IMPLEMENTED $4,321 $2,500 $4,321
117,526
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs