Assessment Year | 1999 |
---|---|
Principal Product | Applied Coatings |
NAICS |
n/a
|
SIC | 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 44 |
Plant Area |
75,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 4,400
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $63,352 | 1,272,567 |
kWh
|
$0.050 |
Electricity Demand | $25,904 | 4,603 |
kW-mo/yr
|
$5.63 |
Electricity Fees | $3,635 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $17,641 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $416 | $900 |
$238
4,689
kWh
|
$178
-
kW-mo/yr
|
|
02 | 2.4113: Install motor voltage controller on lightly loaded motors | $4,051 | $3,290 |
$3,071
61,841
kWh
|
$980
-
kW-mo/yr
|
|
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,972 | $800 |
$10,972
220,399
kWh
|
- | |
04 | 2.6218: Turn off equipment when not in use | $2,202 | - |
$2,202
44,256
kWh
|
- | |
TOTAL RECOMMENDED | $17,641 | $4,990 |
$16,483
331,185
kWh
|
$1,158
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs