Assessment Year | 1999 |
---|---|
Principal Product | Cabinets and Custom Millwork |
NAICS |
n/a
|
SIC | 2431: Millwork |
Sales Range | $5 M to 10M |
# of Employees | 37 |
Plant Area |
14,500
ft2
|
Annual Production | 35,000,000
units
|
Production Hrs. Annual | 2,704
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $24,399 | 308,617 |
kWh
|
$0.079 |
Electricity Demand | $1,303 | 1,819 |
kW-mo/yr
|
$0.72 |
Electricity Fees | $(-2,348.0) | - |
|
- |
Natural Gas | $4,172 | 591 |
MMBtu
|
$7.06 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $7,584 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $925 | $2,165 |
$881
11,137
kWh
|
$44
-
kW-mo/yr
|
- | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $140 | $50 |
$128
1,758
kWh
|
$12
-
kW-mo/yr
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $617 | $300 |
$617
7,913
kWh
|
- | - | |
04 | 2.4113: Install motor voltage controller on lightly loaded motors | $891 | $3,780 |
$855
10,844
kWh
|
$36
-
kW-mo/yr
|
- | |
05 | 2.7314: Reduce ventilation air | $4,902 | $10 |
$4,682
59,496
kWh
|
$220
-
kW-mo/yr
|
- | |
06 | 2.1116: Improve combustion control capability | $109 | $10 | - | - |
$109
-
MMBtu
|
|
TOTAL RECOMMENDED | $7,584 | $6,315 |
$7,163
91,148
kWh
|
$312
-
kW-mo/yr
|
$109
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs