ITAC Assessment: OD0127
ITAC logo
ITAC Assessment: OD0127
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Commercial Printing
NAICS
n/a
SIC 2752: Commercial Printing, Lithographic
Sales Range $1
M
to 5
M
# of Employees 80
Plant Area 150,000
ft2
Annual Production 0
units
Production Hrs. Annual 3,600
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $113,796 5,307,151
kWh
Electricity Demand $143,311 11,229
kW-mo/yr
Electricity Fees $10,710 -
Natural Gas $7,011 784
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $16,583 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,106

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings One-time Revenue or Avoided Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,954 $5,472 $1,428
66,823
kWh
$1,526
-
kW-mo/yr
- - -
02 2.6214: Shut off pilots in standby equipment $477 $80 - - $477
-
MMBtu
- -
03 3.4154: Eliminate leaks in water lines and valves $3,582 $240 $821
38,394
kWh
- - $2,761
-
Tgal
-
04 2.8112: Combine utility meters $9,570 $5,000 - - - - $9,570
TOTAL RECOMMENDED $16,583 $10,792 $2,249
105,217
kWh
$1,526
-
kW-mo/yr
$477
-
MMBtu
$2,761
-
Tgal
$9,570
TOTAL IMPLEMENTED $16,106 $10,712 $2,249
105,217
kWh
$1,526
-
kW-mo/yr
- $2,761
-
Tgal
$9,570
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs