Assessment Year | 1999 |
---|---|
Principal Product | Commercial Printing |
NAICS |
n/a
|
SIC | 2752: Commercial Printing, Lithographic |
Sales Range | $1 M to 5M |
# of Employees | 80 |
Plant Area |
150,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 3,600
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $113,796 | 5,307,151 |
kWh
|
$0.021 |
Electricity Demand | $143,311 | 11,229 |
kW-mo/yr
|
$12.76 |
Electricity Fees | $10,710 | - |
|
- |
Natural Gas | $7,011 | 784 |
MMBtu
|
$8.94 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $16,583 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,106 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,954 | $5,472 |
$1,428
66,823
kWh
|
$1,526
-
kW-mo/yr
|
- | - | - | |
02 | 2.6214: Shut off pilots in standby equipment | $477 | $80 | - | - |
$477
-
MMBtu
|
- | - | |
03 | 3.4154: Eliminate leaks in water lines and valves | $3,582 | $240 |
$821
38,394
kWh
|
- | - |
$2,761
-
Tgal
|
- | |
04 | 2.8112: Combine utility meters | $9,570 | $5,000 | - | - | - | - | $9,570 | |
TOTAL RECOMMENDED | $16,583 | $10,792 |
$2,249
105,217
kWh
|
$1,526
-
kW-mo/yr
|
$477
-
MMBtu
|
$2,761
-
Tgal
|
$9,570 | ||
TOTAL IMPLEMENTED | $16,106 | $10,712 |
$2,249
105,217
kWh
|
$1,526
-
kW-mo/yr
|
- |
$2,761
-
Tgal
|
$9,570 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs