| Assessment Year | 2017 |
|---|---|
| Principal Product | Starch |
| NAICS | 325612: Polish and Other Sanitation Good Manufacturing |
| SIC | 2842: Specialty Cleaning, Polishing, and Sanitation Preparations |
| Sales Range | $50 M to 100M |
| # of Employees | 120 |
| Plant Area |
145,000
ft2
|
| Annual Production | 40,000,000
pieces
|
| Production Hrs. Annual | 3,380
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $154,701 | 1,530,139 |
kWh
|
$0.10 | |
| Electricity Demand | $47,165 | 5,376 |
kW-mo/yr
|
$8.77 | |
| Electricity Fees | $3,022 | - |
|
- | |
| Natural Gas | $75,265 | 10,609 |
MMBtu
|
$7.09 | |
| Waste Disposal Costs | |||||
| Water Usage | $100,666 | 15,650 |
Tgal
|
$6.43 | |
| TOTAL YEARLY COSTS | $380,819 | ||||
| RECOMMENDED SAVINGS* | $34,101 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $33,476 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 3.4154: Eliminate leaks in water lines and valves | $20,062 | - | - | - | - |
$20,062
-
Tgal
|
- | |
| 02 | 2.2437: Recover waste heat from equipment | $7,002 | $1,080 |
$5,353
52,948
kWh
|
$1,649
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,092 | $1,772 |
$3,171
31,377
kWh
|
$977
-
kW-mo/yr
|
- | - | $(-56.0) | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,423 | $280 |
$936
9,258
kWh
|
$487
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $897 | $340 |
$686
6,780
kWh
|
$211
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.2515: Use optimum thickness insulation | $625 | $651 | - | - |
$625
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $34,101 | $4,123 |
$10,146
100,363
kWh
|
$3,324
-
kW-mo/yr
|
$625
-
MMBtu
|
$20,062
-
Tgal
|
$(-56.0) | ||
| TOTAL IMPLEMENTED | $33,476 | $3,472 |
$10,146
100,363
kWh
|
$3,324
-
kW-mo/yr
|
- |
$20,062
-
Tgal
|
$(-56.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs