Assessment Year | 1998 |
---|---|
Principal Product | Processed Vegetables |
NAICS |
n/a
|
SIC | 2099: Food Preparations, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 120 |
Plant Area |
55,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 2,063
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $52,189 | 1,235,639 |
kWh
|
$0.042 |
Electricity Demand | $16,312 | 2,898 |
kW-mo/yr
|
$5.63 |
Electricity Fees | $8,869 | - |
|
- |
Natural Gas | $2,994 | 377 |
MMBtu
|
$7.94 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $14,402 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,935 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,935 | $6,012 |
$1,711
40,445
kWh
|
$1,224
-
kW-mo/yr
|
- | |
02 | 2.4113: Install motor voltage controller on lightly loaded motors | $437 | $1,290 |
$79
4,982
kWh
|
$358
-
kW-mo/yr
|
- | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,225 | $5,625 |
$3,225
76,495
kWh
|
- | - | |
04 | 3.4116: Meter recycled water (to reduce sewer charges) | $7,805 | $4,595 | - | - |
$7,805
-
Tgal
|
|
TOTAL RECOMMENDED | $14,402 | $17,522 |
$5,015
121,922
kWh
|
$1,582
-
kW-mo/yr
|
$7,805
-
Tgal
|
||
TOTAL IMPLEMENTED | $2,935 | $6,012 |
$1,711
40,445
kWh
|
$1,224
-
kW-mo/yr
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs