| Assessment Year | 1998 |
|---|---|
| Principal Product | Paper Moisture Barriers |
| NAICS |
n/a
|
| SIC | 2672: Coated and Laminated Paper, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 105 |
| Plant Area |
300,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $61,337 | 3,848,769 |
kWh
|
$0.016 |
| Electricity Demand | $106,193 | 7,007 |
kW-mo/yr
|
$15.16 |
| Electricity Fees | $2,471 | - |
|
- |
| Natural Gas | $72,643 | 11,895 |
MMBtu
|
$6.11 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $29,608 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $24,320 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Consumption Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,192 | $6,908 |
$4,853
305,100
kWh
|
$6,339
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4113: Install motor voltage controller on lightly loaded motors | $3,843 | $9,910 |
$1,402
88,218
kWh
|
$2,441
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.7224: Reduce space conditioning during non-working hours | $241 | $420 |
$241
15,240
kWh
|
- | - | - | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $365 | $220 |
$365
22,860
kWh
|
- | - | - | - | |
| 05 | 2.2113: Repair or replace steam traps | $672 | $110 | - | - |
$672
-
MMBtu
|
- | - | |
| 06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,833 | $1,495 | - | - |
$1,833
-
MMBtu
|
- | - | |
| 07 | 2.2111: Install steam trap | $1,445 | $560 | - | - |
$1,226
-
MMBtu
|
$219
-
Tgal
|
- | |
| 08 | 2.4156: Establish a preventative maintenance program | $10,017 | $2,800 | - | - | - | - | $10,017 | |
| TOTAL RECOMMENDED | $29,608 | $22,423 |
$6,861
431,418
kWh
|
$8,780
-
kW-mo/yr
|
$3,731
-
MMBtu
|
$219
-
Tgal
|
$10,017 | ||
| TOTAL IMPLEMENTED | $24,320 | $11,953 |
$5,459
343,200
kWh
|
$6,339
-
kW-mo/yr
|
$2,505
-
MMBtu
|
- | $10,017 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Consumption Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs