| Assessment Year | 1998 |
|---|---|
| Principal Product | Aerospace Models |
| NAICS |
n/a
|
| SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 70 |
| Plant Area |
41,000
ft2
|
| Annual Production | 20
pieces
|
| Production Hrs. Annual | 6,760
hrs
|
| Location (State) | Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $35,857 | 701,641 |
kWh
|
$0.051 |
| Electricity Demand | $13,090 | 2,328 |
kW-mo/yr
|
$5.62 |
| Electricity Fees | $539 | - |
|
- |
| Natural Gas | $2,978 | 404 |
MMBtu
|
$7.37 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $25,768 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,679 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,198 | $1,457 |
$2,224
42,790
kWh
|
$974
-
kW-mo/yr
|
- | - | |
| 02 | 2.7132: Install timers on light switches in little used areas | $143 | $80 |
$112
2,052
kWh
|
$31
-
kW-mo/yr
|
- | - | |
| 03 | 2.6214: Shut off pilots in standby equipment | $35 | $10 | - | - |
$35
-
MMBtu
|
- | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,303 | $509 |
$2,729
52,462
kWh
|
$574
-
kW-mo/yr
|
- | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,123 | $50 |
$516
9,965
kWh
|
$607
-
kW-mo/yr
|
- | - | |
| 06 | 2.2437: Recover waste heat from equipment | $538 | $1,010 | - | - |
$538
-
MMBtu
|
- | |
| 07 | 4.322: Eliminate old stock and modify inventory control | $17,428 | $9,180 | - | - | - | $17,428 | |
| TOTAL RECOMMENDED | $25,768 | $12,296 |
$5,581
107,269
kWh
|
$2,186
-
kW-mo/yr
|
$573
-
MMBtu
|
$17,428 | ||
| TOTAL IMPLEMENTED | $6,679 | $2,056 |
$5,065
97,304
kWh
|
$1,579
-
kW-mo/yr
|
$35
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs