ITAC Assessment: OD0114
ITAC logo
ITAC Assessment: OD0114
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Aerospace Models
NAICS
n/a
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 70
Plant Area 41,000
ft2
Annual Production 20
pieces
Production Hrs. Annual 6,760
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $35,857 701,641
kWh
Electricity Demand $13,090 2,328
kW-mo/yr
Electricity Fees $539 -
Natural Gas $2,978 404
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $25,768 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,679

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $3,198 $1,457 $2,224
42,790
kWh
$974
-
kW-mo/yr
- -
02 2.7132: Install timers on light switches in little used areas $143 $80 $112
2,052
kWh
$31
-
kW-mo/yr
- -
03 2.6214: Shut off pilots in standby equipment $35 $10 - - $35
-
MMBtu
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,303 $509 $2,729
52,462
kWh
$574
-
kW-mo/yr
- -
05 2.4231: Reduce the pressure of compressed air to the minimum required $1,123 $50 $516
9,965
kWh
$607
-
kW-mo/yr
- -
06 2.2437: Recover waste heat from equipment $538 $1,010 - - $538
-
MMBtu
-
07 4.322: Eliminate old stock and modify inventory control $17,428 $9,180 - - - $17,428
TOTAL RECOMMENDED $25,768 $12,296 $5,581
107,269
kWh
$2,186
-
kW-mo/yr
$573
-
MMBtu
$17,428
TOTAL IMPLEMENTED $6,679 $2,056 $5,065
97,304
kWh
$1,579
-
kW-mo/yr
$35
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs