ITAC Assessment: OD0113
ITAC logo
ITAC Assessment: OD0113
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Printed Material
NAICS
n/a
SIC 2752: Commercial Printing, Lithographic
Sales Range $10
M
to 50
M
# of Employees 170
Plant Area 190,000
ft2
Annual Production 10,000,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Maryland

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $150,489 4,114,303
kWh
Electricity Demand $68,151 8,699
kW-mo/yr
Electricity Fees $25,615 -
Natural Gas $53,272 8,243
MMBtu
LPG $11,333 1,148
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $75,189 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $50,370

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 3.1161: Eliminate/reduce an operation $22,713 - - - - $22,713
-
MMBtu
02 2.4131: Size electric motors for peak operating efficiency $15,720 $21,621 $10,958
256,155
kWh
$4,762
-
kW-mo/yr
- -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,820 $1,091 $1,308
30,481
kWh
$512
-
kW-mo/yr
- -
04 2.7132: Install timers on light switches in little used areas $209 $250 $209
4,982
kWh
- - -
05 2.7314: Reduce ventilation air $1,897 - $986
23,154
kWh
$911
-
kW-mo/yr
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $23,794 $14,284 $17,055
398,593
kWh
$6,739
-
kW-mo/yr
- -
07 2.3212: Optimize plant power factor $9,036 $50,000 - - $9,036 -
TOTAL RECOMMENDED $75,189 $87,246 $30,516
713,365
kWh
$12,924
-
kW-mo/yr
$9,036 $22,713
-
MMBtu
TOTAL IMPLEMENTED $50,370 $86,996 $29,321
685,229
kWh
$12,013
-
kW-mo/yr
$9,036 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs