Assessment Year | 1998 |
---|---|
Principal Product | Printed Material |
NAICS |
n/a
|
SIC | 2752: Commercial Printing, Lithographic |
Sales Range | $10 M to 50M |
# of Employees | 170 |
Plant Area |
190,000
ft2
|
Annual Production | 10,000,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Maryland |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $150,489 | 4,114,303 |
kWh
|
$0.037 |
Electricity Demand | $68,151 | 8,699 |
kW-mo/yr
|
$7.83 |
Electricity Fees | $25,615 | - |
|
- |
Natural Gas | $53,272 | 8,243 |
MMBtu
|
$6.46 |
LPG | $11,333 | 1,148 |
MMBtu
|
$9.87 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $75,189 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $50,370 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 3.1161: Eliminate/reduce an operation | $22,713 | - | - | - | - |
$22,713
-
MMBtu
|
|
02 | 2.4131: Size electric motors for peak operating efficiency | $15,720 | $21,621 |
$10,958
256,155
kWh
|
$4,762
-
kW-mo/yr
|
- | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,820 | $1,091 |
$1,308
30,481
kWh
|
$512
-
kW-mo/yr
|
- | - | |
04 | 2.7132: Install timers on light switches in little used areas | $209 | $250 |
$209
4,982
kWh
|
- | - | - | |
05 | 2.7314: Reduce ventilation air | $1,897 | - |
$986
23,154
kWh
|
$911
-
kW-mo/yr
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $23,794 | $14,284 |
$17,055
398,593
kWh
|
$6,739
-
kW-mo/yr
|
- | - | |
07 | 2.3212: Optimize plant power factor | $9,036 | $50,000 | - | - | $9,036 | - | |
TOTAL RECOMMENDED | $75,189 | $87,246 |
$30,516
713,365
kWh
|
$12,924
-
kW-mo/yr
|
$9,036 |
$22,713
-
MMBtu
|
||
TOTAL IMPLEMENTED | $50,370 | $86,996 |
$29,321
685,229
kWh
|
$12,013
-
kW-mo/yr
|
$9,036 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs