| Assessment Year | 1998 |
|---|---|
| Principal Product | Printed Material |
| NAICS |
n/a
|
| SIC | 2752: Commercial Printing, Lithographic |
| Sales Range | $10 M to 50M |
| # of Employees | 170 |
| Plant Area |
190,000
ft2
|
| Annual Production | 10,000,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Maryland |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $150,489 | 4,114,303 |
kWh
|
$0.037 |
| Electricity Demand | $68,151 | 8,699 |
kW-mo/yr
|
$7.83 |
| Electricity Fees | $25,615 | - |
|
- |
| Natural Gas | $53,272 | 8,243 |
MMBtu
|
$6.46 |
| LPG | $11,333 | 1,148 |
MMBtu
|
$9.87 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $75,189 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $50,370 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 3.1161: Eliminate/reduce an operation | $22,713 | - | - | - | - |
$22,713
-
MMBtu
|
|
| 02 | 2.4131: Size electric motors for peak operating efficiency | $15,720 | $21,621 |
$10,958
256,155
kWh
|
$4,762
-
kW-mo/yr
|
- | - | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,820 | $1,091 |
$1,308
30,481
kWh
|
$512
-
kW-mo/yr
|
- | - | |
| 04 | 2.7132: Install timers on light switches in little used areas | $209 | $250 |
$209
4,982
kWh
|
- | - | - | |
| 05 | 2.7314: Reduce ventilation air | $1,897 | - |
$986
23,154
kWh
|
$911
-
kW-mo/yr
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $23,794 | $14,284 |
$17,055
398,593
kWh
|
$6,739
-
kW-mo/yr
|
- | - | |
| 07 | 2.3212: Optimize plant power factor | $9,036 | $50,000 | - | - | $9,036 | - | |
| TOTAL RECOMMENDED | $75,189 | $87,246 |
$30,516
713,365
kWh
|
$12,924
-
kW-mo/yr
|
$9,036 |
$22,713
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $50,370 | $86,996 |
$29,321
685,229
kWh
|
$12,013
-
kW-mo/yr
|
$9,036 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs