| Assessment Year | 1998 |
|---|---|
| Principal Product | Asphalt |
| NAICS |
n/a
|
| SIC | 2951: Asphalt Paving Mixtures and Blocks |
| Sales Range | $10 M to 50M |
| # of Employees | 160 |
| Plant Area |
150,000
ft2
|
| Annual Production | 270,000
ton
|
| Production Hrs. Annual | 3,744
hrs
|
| Location (State) | Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $36,033 | 688,159 |
kWh
|
$0.052 |
| Electricity Demand | $19,032 | 4,743 |
kW-mo/yr
|
$4.01 |
| Electricity Fees | $10,004 | - |
|
- |
| Natural Gas | $216,054 | 55,470 |
MMBtu
|
$3.89 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $5,814 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,142 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $612 | $1,562 |
$490
9,379
kWh
|
$122
-
kW-mo/yr
|
- | - | |
| 02 | 2.2511: Insulate bare equipment | $1,672 | $3,000 | - | - |
$1,672
-
MMBtu
|
- | |
| 03 | 3.6124: Burn waste oil for heat | $3,530 | $6,245 | - | - | - |
$3,530
-
gal
|
|
| TOTAL RECOMMENDED | $5,814 | $10,807 |
$490
9,379
kWh
|
$122
-
kW-mo/yr
|
$1,672
-
MMBtu
|
$3,530
-
gal
|
||
| TOTAL IMPLEMENTED | $4,142 | $7,807 |
$490
9,379
kWh
|
$122
-
kW-mo/yr
|
- |
$3,530
-
gal
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs