Assessment Year | 1998 |
---|---|
Principal Product | Aluminum Seals |
NAICS |
n/a
|
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 134 |
Plant Area |
90,000
ft2
|
Annual Production | 30,000
pieces
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $90,910 | 1,868,406 |
kWh
|
$0.049 |
Electricity Demand | $30,433 | 5,582 |
kW-mo/yr
|
$5.45 |
Electricity Fees | $5,172 | - |
|
- |
Natural Gas | $121,798 | 13,760 |
MMBtu
|
$8.85 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $15,169 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,047 | $8,241 |
$3,823
148,886
kWh
|
$2,224
-
kW-mo/yr
|
- | - | |
02 | 2.2437: Recover waste heat from equipment | $809 | $200 | - | - |
$809
-
MMBtu
|
- | |
03 | 2.7224: Reduce space conditioning during non-working hours | $453 | $98 | - | - |
$453
-
MMBtu
|
- | |
04 | 2.7232: Replace existing hvac unit with high efficiency model | $5,445 | $11,000 |
$5,445
111,958
kWh
|
- | - | - | |
05 | 2.4314: Use synthetic lubricant | $270 | $59 |
$210
4,396
kWh
|
$60
-
kW-mo/yr
|
- | - | |
06 | 4.624: Hire additional personnel to reduce changeout time | $2,145 | $500 | - | - | - | $2,145 | |
TOTAL RECOMMENDED | $15,169 | $20,098 |
$9,478
265,240
kWh
|
$2,284
-
kW-mo/yr
|
$1,262
-
MMBtu
|
$2,145 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs