ITAC Assessment: OD0104
ITAC logo
ITAC Assessment: OD0104
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Aluminum Seals
NAICS
n/a
SIC 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 134
Plant Area 90,000
ft2
Annual Production 30,000
pieces
Production Hrs. Annual 4,420
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $90,910 1,868,406
kWh
Electricity Demand $30,433 5,582
kW-mo/yr
Electricity Fees $5,172 -
Natural Gas $121,798 13,760
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,169 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Primary Product Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $6,047 $8,241 $3,823
148,886
kWh
$2,224
-
kW-mo/yr
- -
02 2.2437: Recover waste heat from equipment $809 $200 - - $809
-
MMBtu
-
03 2.7224: Reduce space conditioning during non-working hours $453 $98 - - $453
-
MMBtu
-
04 2.7232: Replace existing hvac unit with high efficiency model $5,445 $11,000 $5,445
111,958
kWh
- - -
05 2.4314: Use synthetic lubricant $270 $59 $210
4,396
kWh
$60
-
kW-mo/yr
- -
06 4.624: Hire additional personnel to reduce changeout time $2,145 $500 - - - $2,145
TOTAL RECOMMENDED $15,169 $20,098 $9,478
265,240
kWh
$2,284
-
kW-mo/yr
$1,262
-
MMBtu
$2,145
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs