Assessment Year | 1997 |
---|---|
Principal Product | Corrugated Containers |
NAICS |
n/a
|
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $10 M to 50M |
# of Employees | 170 |
Plant Area |
149,200
ft2
|
Annual Production | 720,000
thousand feet
|
Production Hrs. Annual | 6,864
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $82,495 | 4,129,836 |
kWh
|
$0.020 |
Electricity Demand | $121,798 | 18,266 |
kW-mo/yr
|
$6.67 |
Electricity Fees | $40,320 | - |
|
- |
Natural Gas | $28,953 | 19,454 |
MMBtu
|
$1.49 |
LPG | $28,953 | 3,322 |
MMBtu
|
$8.72 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $26,349 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,502 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,007 | $11,490 |
$3,163
158,265
kWh
|
$1,844
-
kW-mo/yr
|
- | - | |
02 | 2.1212: Operate boilers on high fire setting | $1,495 | $1,495 | - | - |
$1,495
-
MMBtu
|
- | |
03 | 2.2696: Use excess cold process fluid for industrial cooling needs | $19,847 | $8,500 | - | - | - |
$19,847
-
Tgal
|
|
TOTAL RECOMMENDED | $26,349 | $21,485 |
$3,163
158,265
kWh
|
$1,844
-
kW-mo/yr
|
$1,495
-
MMBtu
|
$19,847
-
Tgal
|
||
TOTAL IMPLEMENTED | $6,502 | $12,985 |
$3,163
158,265
kWh
|
$1,844
-
kW-mo/yr
|
$1,495
-
MMBtu
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs