ITAC Assessment: OD0094
ITAC logo
ITAC Assessment: OD0094
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Wood Kitchen Cabinets
NAICS
n/a
SIC 2434: Wood Kitchen Cabinets
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 140,000
ft2
Annual Production 140,438
pieces
Production Hrs. Annual 2,210
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $86,713 1,475,381
kWh
Electricity Demand $48,802 5,885
kW-mo/yr
Electricity Fees $8,817 -
Natural Gas $20,076 5,022
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $30,467 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,444

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $6,901 $24,756 $2,101
106,682
kWh
$4,800
-
kW-mo/yr
-
02 2.7134: Use photocell controls $543 $778 $543
9,379
kWh
- -
03 3.6122: Install solid waste incinerator for heat $23,023 $75,016 - - $23,023
-
lb
TOTAL RECOMMENDED $30,467 $100,550 $2,644
116,061
kWh
$4,800
-
kW-mo/yr
$23,023
-
lb
TOTAL IMPLEMENTED $7,444 $25,534 $2,644
116,061
kWh
$4,800
-
kW-mo/yr
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs