Assessment Year | 1996 |
---|---|
Principal Product | Marine Air Conditioning Units |
NAICS |
n/a
|
SIC | 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment |
Sales Range | $10 M to 50M |
# of Employees | 110 |
Plant Area |
60,000
ft2
|
Annual Production | 28,815
pieces
|
Production Hrs. Annual | 4,624
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $37,223 | 741,794 |
kWh
|
$0.050 |
Electricity Demand | $19,255 | 3,102 |
kW-mo/yr
|
$6.21 |
Electricity Fees | $2,628 | - |
|
- |
Fuel Oil #2 | $10,354 | 1,737 |
MMBtu
|
$5.96 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $19,115 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,569 | $10,531 |
$4,036
45,721
kWh
|
$1,533
-
kW-mo/yr
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,019 | $400 |
$3,019
60,082
kWh
|
- | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $895 | - |
$895
17,878
kWh
|
- | - | - | |
04 | 2.2514: Cover open tanks | $1,328 | $1,030 |
$1,328
26,377
kWh
|
- | - | - | |
05 | 2.7261: Install timers and/or thermostats | $1,088 | $380 |
$330
6,448
kWh
|
- |
$758
-
MMBtu
|
- | |
06 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $2,136 | - | - | - | - |
$2,136
-
lb
|
|
07 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $5,080 | - | - | - | - |
$5,080
-
lb
|
|
TOTAL RECOMMENDED | $19,115 | $12,341 |
$9,608
156,506
kWh
|
$1,533
-
kW-mo/yr
|
$758
-
MMBtu
|
$7,216
-
lb
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs