ITAC Assessment: OD0064
ITAC logo
ITAC Assessment: OD0064
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Softboard sheathing
NAICS
n/a
SIC 2499: Wood Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 122
Plant Area 200,000
ft2
Annual Production 240,000
thousand feet
Production Hrs. Annual 8,568
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $990,943 58,804,807
kWh
Electricity Demand $1,389,833 224,337
kW-mo/yr
Electricity Fees $86,122 -
Coal $536,369 489,188
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $472,755 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Product Savings
01 2.4133: Use most efficient type of electric motors $5,023 $11,843 $3,324
196,659
kWh
$1,699
-
kW-mo/yr
- - -
02 4.114: Add/modify equipment to improve drying process $308,827 $235,200 $(-113,522.0)
(-6,717,468)
kWh
$(-55,651.0)
-
kW-mo/yr
- $(-2,000.0) $480,000
03 2.7142: Utilize higher efficiency lamps and/or ballasts $13,695 $24,130 $8,266
489,156
kWh
$5,429
-
kW-mo/yr
- - -
04 2.7132: Install timers on light switches in little used areas $3,454 $639 $3,454
204,279
kWh
- - - -
05 2.3134: Shift from daytime to nighttime operation $124,620 $208,110 - $124,620
-
kW-mo/yr
- - -
06 3.5313: Increase amount of waste recovered for resale $17,136 - - - $17,136
-
lb
- -
TOTAL RECOMMENDED $472,755 $479,922 $(-98,478.0)
(-5,827,374)
kWh
$76,097
-
kW-mo/yr
$17,136
-
lb
$(-2,000.0) $480,000
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs