ITAC Assessment: OD0060
ITAC logo
ITAC Assessment: OD0060
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Dyed and wound textile products
NAICS
n/a
SIC 2282: Yarn Texturizing, Throwing, Twisting, and Winding Mills
Sales Range $5
M
to 10
M
# of Employees 124
Plant Area 61,850
ft2
Annual Production 4,200,000
lb
Production Hrs. Annual 5,760
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $117,333 5,814,771
kWh
Electricity Demand $182,278 15,128
kW-mo/yr
Electricity Fees $32,418 -
Fuel Oil #6 $438,500 71,679
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $21,653 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Fuel Oil #6 Savings Solid Waste (non-haz) Savings
01 2.4133: Use most efficient type of electric motors $4,887 $8,091 n/a $2,176
107,855
kWh
$2,711
-
kW-mo/yr
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,032 $5,275 n/a $812
40,152
kWh
$1,220
-
kW-mo/yr
- -
03 2.1233: Analyze flue gas for proper air/fuel ratio $14,604 $1,495 n/a - - $14,604
-
MMBtu
-
04 3.5316: Contract a wood pallet recycling company $130 - n/a - - - $130
-
lb
TOTAL RECOMMENDED $21,653 $14,861 $2,988
148,007
kWh
$3,931
-
kW-mo/yr
$14,604
-
MMBtu
$130
-
lb
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs