| Assessment Year | 1996 |
|---|---|
| Principal Product | Calcium aluminate cements |
| NAICS |
n/a
|
| SIC | 3297: Nonclay Refractories |
| Sales Range | $10 M to 50M |
| # of Employees | 99 |
| Plant Area |
200,000
ft2
|
| Annual Production | 100,000
ton
|
| Production Hrs. Annual | 8,232
hrs
|
| Location (State) | Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $231,232 | 13,266,120 |
kWh
|
$0.017 |
| Electricity Demand | $302,416 | 54,695 |
kW-mo/yr
|
$5.53 |
| Electricity Fees | $24,094 | - |
|
- |
| Natural Gas | $194,225 | 76,730 |
MMBtu
|
$2.53 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $32,346 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,339 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2511: Insulate bare equipment | $21,127 | $16,700 | - | - |
$21,127
-
MMBtu
|
- | |
| 02 | 2.4133: Use most efficient type of electric motors | $2,002 | $5,256 |
$1,266
72,685
kWh
|
$736
-
kW-mo/yr
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $885 | $2,412 |
$476
27,257
kWh
|
$409
-
kW-mo/yr
|
- | - | |
| 04 | 2.7134: Use photocell controls | $581 | $388 |
$548
35,463
kWh
|
$33
-
kW-mo/yr
|
- | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,452 | $1,200 |
$6,452
372,216
kWh
|
- | - | - | |
| 06 | 3.6124: Burn waste oil for heat | $1,299 | $3,360 | - | - |
$859
-
MMBtu
|
$440
-
gal
|
|
| TOTAL RECOMMENDED | $32,346 | $29,316 |
$8,742
507,621
kWh
|
$1,178
-
kW-mo/yr
|
$21,986
-
MMBtu
|
$440
-
gal
|
||
| TOTAL IMPLEMENTED | $9,339 | $8,868 |
$8,194
472,158
kWh
|
$1,145
-
kW-mo/yr
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs