ITAC Assessment: OD0058
ITAC logo
ITAC Assessment: OD0058
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Calcium aluminate cements
NAICS
n/a
SIC 3297: Nonclay Refractories
Sales Range $10
M
to 50
M
# of Employees 99
Plant Area 200,000
ft2
Annual Production 100,000
ton
Production Hrs. Annual 8,232
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $231,232 13,266,120
kWh
Electricity Demand $302,416 54,695
kW-mo/yr
Electricity Fees $24,094 -
Natural Gas $194,225 76,730
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $32,346 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,339

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings
01 2.2511: Insulate bare equipment $21,127 $16,700 - - $21,127
-
MMBtu
-
02 2.4133: Use most efficient type of electric motors $2,002 $5,256 $1,266
72,685
kWh
$736
-
kW-mo/yr
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $885 $2,412 $476
27,257
kWh
$409
-
kW-mo/yr
- -
04 2.7134: Use photocell controls $581 $388 $548
35,463
kWh
$33
-
kW-mo/yr
- -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,452 $1,200 $6,452
372,216
kWh
- - -
06 3.6124: Burn waste oil for heat $1,299 $3,360 - - $859
-
MMBtu
$440
-
gal
TOTAL RECOMMENDED $32,346 $29,316 $8,742
507,621
kWh
$1,178
-
kW-mo/yr
$21,986
-
MMBtu
$440
-
gal
TOTAL IMPLEMENTED $9,339 $8,868 $8,194
472,158
kWh
$1,145
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs