Assessment Year | 1995 |
---|---|
Principal Product | Paper Converting |
NAICS |
n/a
|
SIC | 2679: Converted Paper and Paperboard Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
200,000
ft2
|
Annual Production | 108,000,000
lb
|
Production Hrs. Annual | 6,120
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $104,687 | 1,767,585 |
kWh
|
$0.059 |
Fuel Oil #2 | $14,309 | 3,920 |
MMBtu
|
$3.65 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $13,328 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,462 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,053 | $726 |
$4,053
68,288
kWh
|
- | |
02 | 2.2437: Recover waste heat from equipment | $2,607 | $635 | - |
$2,607
-
MMBtu
|
|
03 | 2.4133: Use most efficient type of electric motors | $612 | $748 |
$612
10,258
kWh
|
- | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $720 | $1,035 |
$720
12,016
kWh
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,883 | $480 |
$1,883
31,946
kWh
|
- | |
06 | 2.7135: Install occupancy sensors | $545 | $433 |
$545
9,086
kWh
|
- | |
07 | 2.6218: Turn off equipment when not in use | $477 | - |
$477
8,206
kWh
|
- | |
08 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $994 | - |
$994
-
kWh
|
- | |
09 | 2.6218: Turn off equipment when not in use | $1,437 | $910 |
$1,437
24,326
kWh
|
- | |
TOTAL RECOMMENDED | $13,328 | $4,967 |
$10,721
164,126
kWh
|
$2,607
-
MMBtu
|
||
TOTAL IMPLEMENTED | $8,462 | $2,864 |
$8,462
143,024
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #2 Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs