ITAC Assessment: OD0012
ITAC logo
ITAC Assessment: OD0012
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Pressure Treated Lumber
NAICS
n/a
SIC 2491: Wood Preserving
Sales Range $5
M
to 10
M
# of Employees 50
Plant Area 110,000
ft2
Annual Production 44,000,000
thousand feet
Production Hrs. Annual 4,530
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $100,825 1,111,079
kWh
Natural Gas $6,731 979
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $7,913 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.2625: Chill water to the highest temperature possible $1,145 $100 $1,145
12,603
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $3,578 $9,144 $3,578
39,566
kWh
03 2.4133: Use most efficient type of electric motors $2,282 $4,025 $2,282
25,205
kWh
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $908 $577 $908
9,965
kWh
TOTAL RECOMMENDED $7,913 $13,846 $7,913
87,339
kWh
TOTAL IMPLEMENTED - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs