ITAC Assessment: OD0011
ITAC logo
ITAC Assessment: OD0011
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Micro floppy disks
NAICS
n/a
SIC 3577: Computer Peripheral Equipment, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 250
Plant Area 100,000
ft2
Annual Production 160,000,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $441,001 8,494,432
kWh
Natural Gas $28,034 4,520
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $65,347 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $64,686

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $38,569 $77,523 $38,569
742,673
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $661 $683 $661
9,379
kWh
-
03 2.1311: Replace electrically-operated equipment with fossil fuel equipment $16,089 $3,300 $39,549
759,086
kWh
$(-23,460.0)
-
MMBtu
04 2.4133: Use most efficient type of electric motors $5,394 $9,618 $5,394
103,751
kWh
-
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,970 $927 $1,970
37,808
kWh
-
06 2.6212: Turn off equipment during breaks, reduce operating time $1,613 $860 $1,613
31,067
kWh
-
07 2.3132: Recharge batteries on during off-peak demand periods $1,051 - $1,051
-
kWh
-
TOTAL RECOMMENDED $65,347 $92,911 $88,807
1,683,764
kWh
$(-23,460.0)
-
MMBtu
TOTAL IMPLEMENTED $64,686 $92,228 $88,146
1,674,385
kWh
$(-23,460.0)
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs