ITAC Assessment: OD0003
ITAC logo
ITAC Assessment: OD0003
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product rubber rollers & shaft turnings
NAICS
n/a
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 40
Plant Area 62,400
ft2
Annual Production 0
units
Production Hrs. Annual 4,500
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $97,324 1,321,805
kWh
Natural Gas $18,663 3,195
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,507 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $8,798 $29,976 $8,798
121,923
kWh
-
02 2.7124: Make a practice of turning off lights when not needed $2,032 $1,925 $2,032
28,136
kWh
-
03 2.1233: Analyze flue gas for proper air/fuel ratio $558 $200 - $558
-
MMBtu
04 2.2511: Insulate bare equipment $402 $705 - $402
-
MMBtu
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $717 $1,365 $95
1,465
kWh
$622
-
MMBtu
TOTAL RECOMMENDED $12,507 $34,171 $10,925
151,524
kWh
$1,582
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs