Assessment Year | 2000 |
---|---|
Principal Product | bread, cake, and related products |
NAICS |
n/a
|
SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
20,000
ft2
|
Annual Production | 12,000,000
pieces
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $150,419 | 2,409,000 |
kWh
|
$0.062 |
Electricity Demand | $34,352 | 4,166 |
kW-mo/yr
|
$8.25 |
Electricity Fees | $815 | - |
|
- |
Natural Gas | $94,742 | 17,622 |
MMBtu
|
$5.38 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $135,768 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $23,982 | $160 | n/a |
$19,754
320,047
kWh
|
$4,228
-
kW-mo/yr
|
- |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,550 | - | n/a |
$1,277
20,809
kWh
|
$273
-
kW-mo/yr
|
- |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,700 | $8,947 | n/a |
$3,971
64,478
kWh
|
$729
-
kW-mo/yr
|
- |
04 | 3.5311: Recover and reuse waste material | $99,450 | $400 | n/a | - | - |
$99,450
-
lb
|
05 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $6,086 | $2,074 | n/a | - | - |
$6,086
-
lb
|
TOTAL RECOMMENDED | $135,768 | $11,581 |
$25,002
405,334
kWh
|
$5,230
-
kW-mo/yr
|
$105,536
-
lb
|
||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs