Assessment Year | 2000 |
---|---|
Principal Product | industrial inorganic chemicals |
NAICS |
n/a
|
SIC | 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 84 |
Plant Area |
74,500
ft2
|
Annual Production | 75,400
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Nevada |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $472,398 | 11,507,000 |
kWh
|
$0.041 |
Electricity Demand | $216,089 | 23,080 |
kW-mo/yr
|
$9.36 |
Natural Gas | $1,487,688 | 517,572 |
MMBtu
|
$2.87 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $162,500 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $2,021 | $2,398 | n/a |
$1,536
38,394
kWh
|
$485
-
kW-mo/yr
|
- |
02 | 2.7132: Install timers on light switches in little used areas | $1,105 | $675 | n/a |
$1,105
27,550
kWh
|
- | - |
03 | 3.4154: Eliminate leaks in water lines and valves | $3,756 | - | n/a |
$3,756
75,322
kWh
|
- | - |
04 | 4.441: Install automatic packing equipment | $106,434 | $41,000 | n/a | - | - | $106,434 |
05 | 2.4321: Upgrade obsolete equipment | $49,184 | $25,969 | n/a |
$9,824
272,274
kWh
|
- | $39,360 |
TOTAL RECOMMENDED | $162,500 | $70,042 |
$16,221
413,540
kWh
|
$485
-
kW-mo/yr
|
$145,794 | ||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs