| Assessment Year | 2000 |
|---|---|
| Principal Product | Lime Products |
| NAICS |
n/a
|
| SIC | 3274: Lime |
| Sales Range | $10 M to 50M |
| # of Employees | 65 |
| Plant Area |
n/a
|
| Annual Production | 600,000
ton
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $381,439 | 7,307,151 |
kWh
|
$0.052 |
| Electricity Demand | $260,830 | 23,817 |
kW-mo/yr
|
$10.95 |
| Electricity Fees | $(-20,813.0) | - |
|
- |
| LPG | $40,779 | 4,384 |
MMBtu
|
$9.30 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $16,302 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $13,244 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | LPG Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.1116: Improve combustion control capability | $3,058 | $5,650 | - | - | - |
$3,058
-
MMBtu
|
|
| 02 | 2.3212: Optimize plant power factor | $12,568 | $9,490 |
$7,260
116,647
kWh
|
- | $5,308 | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $676 | $200 |
$140
2,638
kWh
|
$524
-
kW-mo/yr
|
$12 | - | |
| TOTAL RECOMMENDED | $16,302 | $15,340 |
$7,400
119,285
kWh
|
$524
-
kW-mo/yr
|
$5,320 |
$3,058
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $13,244 | $9,690 |
$7,400
119,285
kWh
|
$524
-
kW-mo/yr
|
$5,320 | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs