ITAC Assessment: NV0147
ITAC logo
ITAC Assessment: NV0147
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Rolled Steel Bars
NAICS
n/a
SIC 3556: Food Products Machinery
Sales Range $50
M
to 100
M
# of Employees 85
Plant Area 88,200
ft2
Annual Production 2,500,000
lb
Production Hrs. Annual 4,160
hrs
Location (State) Nevada

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $145,829 3,536,049
kWh
Electricity Demand $120,327 12,500
kW-mo/yr
Electricity Fees $3,510 -
Natural Gas $153,978 37,467
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,287 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,778

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings LPG Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $334 $727 $261
6,448
kWh
$83
-
kW-mo/yr
$(-10.0) - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,444 $300 $1,029
24,912
kWh
$462
-
kW-mo/yr
$(-47.0) - - -
03 2.7231: Use radiant heater for spot heating $3,476 $1,368 $3,484
84,408
kWh
$2,310
-
kW-mo/yr
$(-180.0) - $(-2,138.0)
-
MMBtu
-
04 4.454: Modify startup/shutdown times $13,033 - $3,315
82,943
kWh
- - $7,384
-
MMBtu
- $2,334
TOTAL RECOMMENDED $18,287 $2,395 $8,089
198,711
kWh
$2,855
-
kW-mo/yr
$(-237.0) $7,384
-
MMBtu
$(-2,138.0)
-
MMBtu
$2,334
TOTAL IMPLEMENTED $1,778 $1,027 $1,290
31,360
kWh
$545
-
kW-mo/yr
$(-57.0) - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs