Assessment Year | 1999 |
---|---|
Principal Product | Moulded Wood Products |
NAICS |
n/a
|
SIC | 2431: Millwork |
Sales Range | $10 M to 50M |
# of Employees | 133 |
Plant Area |
134,300
ft2
|
Annual Production | 14,904,954
units
|
Production Hrs. Annual | 4,394
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $239,161 | 3,627,491 |
kWh
|
$0.066 |
Electricity Demand | $120,405 | 11,141 |
kW-mo/yr
|
$10.81 |
Electricity Fees | $14,339 | - |
|
- |
LPG | $36,576 | 5,482 |
MMBtu
|
$6.67 |
Fuel Oil #4 | $2,422 | 438 |
MMBtu
|
$5.53 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $78,746 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $51,413 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | LPG Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Product Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $3,135 | $5,200 | - | - | - |
$3,135
-
MMBtu
|
- | - | - | - | |
02 | 2.3212: Optimize plant power factor | $5,157 | $5,200 |
$5,157
33,118
kWh
|
- | - | - | - | - | - | - | |
03 | 2.4133: Use most efficient type of electric motors | $3,181 | $3,707 |
$1,973
31,946
kWh
|
$1,127
-
kW-mo/yr
|
$81 | - | - | - | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,220 | $1,000 |
$2,653
34,291
kWh
|
$485
-
kW-mo/yr
|
$82 | - | - | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,002 | $27,320 |
$6,202
100,821
kWh
|
$3,546
-
kW-mo/yr
|
$254 | - | - | - | - | - | |
06 | 3.6192: Use a less expensive method of waste removal | $9,039 | - | - | - | - | - |
$9,039
-
lb
|
- | - | - | |
07 | 4.431: Train operators for maximum operating efficiency | $13,552 | $640 | - | - | - | - | - | - | $13,552 | - | |
08 | 4.423: Move product using mechanical means | $31,460 | $32,800 | - | - | - | - | - | $19,860 | - | $11,600 | |
TOTAL RECOMMENDED | $78,746 | $75,867 |
$15,985
200,176
kWh
|
$5,158
-
kW-mo/yr
|
$417 |
$3,135
-
MMBtu
|
$9,039
-
lb
|
$19,860 | $13,552 | $11,600 | ||
TOTAL IMPLEMENTED | $51,413 | $38,147 |
$4,626
66,237
kWh
|
$1,612
-
kW-mo/yr
|
$163 | - | - | $19,860 | $13,552 | $11,600 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | LPG Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Product Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs