ITAC Assessment: NV0145
ITAC logo
ITAC Assessment: NV0145
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Moulded Wood Products
NAICS
n/a
SIC 2431: Millwork
Sales Range $10
M
to 50
M
# of Employees 133
Plant Area 134,300
ft2
Annual Production 14,904,954
units
Production Hrs. Annual 4,394
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $239,161 3,627,491
kWh
Electricity Demand $120,405 11,141
kW-mo/yr
Electricity Fees $14,339 -
LPG $36,576 5,482
MMBtu
Fuel Oil #4 $2,422 438
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $78,746 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $51,413

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings LPG Savings Solid Waste (non-haz) Savings Administrative Changes Savings Primary Product Savings Increase in Production Savings
01 2.2437: Recover waste heat from equipment $3,135 $5,200 - - - $3,135
-
MMBtu
- - - -
02 2.3212: Optimize plant power factor $5,157 $5,200 $5,157
33,118
kWh
- - - - - - -
03 2.4133: Use most efficient type of electric motors $3,181 $3,707 $1,973
31,946
kWh
$1,127
-
kW-mo/yr
$81 - - - - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,220 $1,000 $2,653
34,291
kWh
$485
-
kW-mo/yr
$82 - - - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $10,002 $27,320 $6,202
100,821
kWh
$3,546
-
kW-mo/yr
$254 - - - - -
06 3.6192: Use a less expensive method of waste removal $9,039 - - - - - $9,039
-
lb
- - -
07 4.431: Train operators for maximum operating efficiency $13,552 $640 - - - - - - $13,552 -
08 4.423: Move product using mechanical means $31,460 $32,800 - - - - - $19,860 - $11,600
TOTAL RECOMMENDED $78,746 $75,867 $15,985
200,176
kWh
$5,158
-
kW-mo/yr
$417 $3,135
-
MMBtu
$9,039
-
lb
$19,860 $13,552 $11,600
TOTAL IMPLEMENTED $51,413 $38,147 $4,626
66,237
kWh
$1,612
-
kW-mo/yr
$163 - - $19,860 $13,552 $11,600
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings LPG Savings Solid Waste (non-haz) Savings Administrative Changes Savings Primary Product Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs