ITAC Assessment: NV0141
ITAC logo
ITAC Assessment: NV0141
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Sporting & Athletic Goods
NAICS
n/a
SIC 3949: Sporting and Athletic Goods, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 50
Plant Area 60,000
ft2
Annual Production 8,000,000
pieces
Production Hrs. Annual 2,210
hrs
Location (State) Nevada

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $16,836 403,283
kWh
Electricity Demand $13,558 1,461
kW-mo/yr
Electricity Fees $1,239 -
Natural Gas $11,391 2,175
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,504 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,246

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Solid Waste (non-haz) Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $258 $562 $194
4,689
kWh
$59
-
kW-mo/yr
$5 - -
02 2.7243: Improve air circulation with destratification fans / other methods $4,845 $2,532 $(-115.0)
(-2,638)
kWh
$(-85.0)
-
kW-mo/yr
$(-4.0) $5,049
-
MMBtu
-
03 3.6192: Use a less expensive method of waste removal $3,401 - - - - - $3,401
-
lb
TOTAL RECOMMENDED $8,504 $3,094 $79
2,051
kWh
$(-26.0)
-
kW-mo/yr
$1 $5,049
-
MMBtu
$3,401
-
lb
TOTAL IMPLEMENTED $8,246 $2,532 $(-115.0)
(-2,638)
kWh
$(-85.0)
-
kW-mo/yr
$(-4.0) $5,049
-
MMBtu
$3,401
-
lb
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs