Assessment Year | 1990 |
---|---|
Principal Product | PINE BEDROOM FURNITURE |
NAICS |
n/a
|
SIC | 2511: Wood Household Furniture, Except Upholstered |
Sales Range | $10 M to 50M |
# of Employees | 370 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 2,550
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $351,323 | 4,887,456 |
kWh
|
$0.072 |
Natural Gas | $6,461 | 1,206 |
MMBtu
|
$5.36 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $61,513 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $52,039 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $1,519 | $8,333 |
$1,519
21,395
kWh
|
- | - | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $14,462 | - |
$14,462
204,279
kWh
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,538 | $2,485 |
$917
12,896
kWh
|
- | $621 | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $20,783 | $1,000 |
$20,783
293,376
kWh
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,037 | $200 |
$2,037
26,377
kWh
|
- | - | |
06 | 2.7226: Use computer programs to optimize hvac performance | $15,256 | $1,000 |
$15,256
215,416
kWh
|
- | - | |
07 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $5,918 | $60,000 |
$76,610
1,081,477
kWh
|
$(-65,692.0)
-
MMBtu
|
$(-5,000.0) | |
TOTAL RECOMMENDED | $61,513 | $73,018 |
$131,584
1,855,216
kWh
|
$(-65,692.0)
-
MMBtu
|
$(-4,379.0) | ||
TOTAL IMPLEMENTED | $52,039 | $4,485 |
$51,418
725,967
kWh
|
- | $621 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs