| Assessment Year | 1999 |
|---|---|
| Principal Product | Machine Parts |
| NAICS |
n/a
|
| SIC | 3451: Screw Machine Products |
| Sales Range | $5 M to 10M |
| # of Employees | 70 |
| Plant Area |
27,000
ft2
|
| Annual Production | 12,000,000
lb
|
| Production Hrs. Annual | 7,488
hrs
|
| Location (State) | Nevada |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $27,885 | 668,230 |
kWh
|
$0.042 |
| Electricity Demand | $15,423 | 1,662 |
kW-mo/yr
|
$9.28 |
| Electricity Fees | $1,988 | - |
|
- |
| Natural Gas | $7,656 | 1,420 |
MMBtu
|
$5.39 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $31,257 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $26,960 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $1,544 | $1,000 | - | - | - |
$1,544
-
MMBtu
|
- | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $372 | $300 |
$202
4,689
kWh
|
$163
-
kW-mo/yr
|
$7 | - | - | - | |
| 03 | 2.7144: Install spectral reflectors / delamp | $198 | $25 |
$143
3,517
kWh
|
$51
-
kW-mo/yr
|
$4 | - | - | - | |
| 04 | 2.7231: Use radiant heater for spot heating | $2,377 | $4,576 | - | - | - |
$2,377
-
MMBtu
|
- | - | |
| 05 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $376 | - | - | - | - | - |
$376
-
lb
|
- | |
| 06 | 4.111: Add equipment/ operators to reduce production bottleneck | $26,390 | $7,970 | - | - | - | - | - | $26,390 | |
| TOTAL RECOMMENDED | $31,257 | $13,871 |
$345
8,206
kWh
|
$214
-
kW-mo/yr
|
$11 |
$3,921
-
MMBtu
|
$376
-
lb
|
$26,390 | ||
| TOTAL IMPLEMENTED | $26,960 | $8,295 |
$345
8,206
kWh
|
$214
-
kW-mo/yr
|
$11 | - | - | $26,390 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs