Assessment Year | 1999 |
---|---|
Principal Product | Industrial and Medical Precision Ceramic Products |
NAICS |
n/a
|
SIC | 2951: Asphalt Paving Mixtures and Blocks |
Sales Range | $10 M to 50M |
# of Employees | 95 |
Plant Area |
82,980
ft2
|
Annual Production | 800,000
pieces
|
Production Hrs. Annual | 4,352
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $170,686 | 2,069,461 |
kWh
|
$0.082 |
Electricity Demand | $24,711 | 5,659 |
kW-mo/yr
|
$4.37 |
Electricity Fees | $1,701 | - |
|
- |
Natural Gas | $67,506 | 13,003 |
MMBtu
|
$5.19 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $281,329 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $188,647 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3412: Use waste heat to produce steam to drive a steam turbine-generator | $78,922 | $210,000 |
$79,775
979,191
kWh
|
$11,790
-
kW-mo/yr
|
$196 |
$(-12,839.0)
-
MMBtu
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,392 | $39,424 |
$12,422
152,403
kWh
|
$2,938
-
kW-mo/yr
|
$32 | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,139 | $1,760 |
$1,058
12,896
kWh
|
$78
-
kW-mo/yr
|
$3 | - | - | - | |
04 | 2.7243: Improve air circulation with destratification fans / other methods | $4,402 | $2,405 |
$(-424.0)
(-6,448)
kWh
|
- | - |
$4,826
-
MMBtu
|
- | - | |
05 | 2.8114: Change rate schedules or other changes in utility service | $8,219 | $1,590 | - | - | $8,219 | - | - | - | |
06 | 3.6192: Use a less expensive method of waste removal | $1,012 | - | - | - | - | - | - | $1,012 | |
07 | 4.513: Re-arrange equipment layout to reduce labor costs | $172,243 | $54,000 | - | - | - | - | $172,243 | - | |
TOTAL RECOMMENDED | $281,329 | $309,179 |
$92,831
1,138,042
kWh
|
$14,806
-
kW-mo/yr
|
$8,450 |
$(-8,013.0)
-
MMBtu
|
$172,243 | $1,012 | ||
TOTAL IMPLEMENTED | $188,647 | $93,424 |
$12,422
152,403
kWh
|
$2,938
-
kW-mo/yr
|
$32 | - | $172,243 | $1,012 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs