Assessment Year | 1999 |
---|---|
Principal Product | Asphalt Paving Mixtures, Concrete Ready-Mix |
NAICS |
n/a
|
SIC | 2951: Asphalt Paving Mixtures and Blocks |
Sales Range | $10 M to 50M |
# of Employees | 40 |
Plant Area |
n/a
|
Annual Production | 100,000
ton
|
Production Hrs. Annual | 4,368
hrs
|
Location (State) | Nevada |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $48,667 | 1,114,889 |
kWh
|
$0.044 |
Electricity Demand | $59,932 | 9,460 |
kW-mo/yr
|
$6.34 |
Electricity Fees | $4,270 | - |
|
- |
Natural Gas | $28,159 | 4,515 |
MMBtu
|
$6.24 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $27,434 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,159 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $105 | $200 | - | - | - |
$105
-
MMBtu
|
- | |
02 | 2.3212: Optimize plant power factor | $1,146 | $1,933 | - | - | $1,146 | - | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,277 | $638 |
$836
19,050
kWh
|
$441
-
kW-mo/yr
|
- | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $111 | $80 |
$72
1,758
kWh
|
$39
-
kW-mo/yr
|
- | - | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $327 | - |
$213
4,982
kWh
|
$114
-
kW-mo/yr
|
- | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $444 | $50 |
$289
6,741
kWh
|
$155
-
kW-mo/yr
|
- | - | - | |
07 | 4.444: Install system to collect scrap | $24,024 | $20,320 | - | - | - | - | $24,024 | |
TOTAL RECOMMENDED | $27,434 | $23,221 |
$1,410
32,531
kWh
|
$749
-
kW-mo/yr
|
$1,146 |
$105
-
MMBtu
|
$24,024 | ||
TOTAL IMPLEMENTED | $2,159 | $768 |
$1,410
32,531
kWh
|
$749
-
kW-mo/yr
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs