| Assessment Year | 1999 |
|---|---|
| Principal Product | Commercial Printing, Lithographic |
| NAICS |
n/a
|
| SIC | 2752: Commercial Printing, Lithographic |
| Sales Range | $1 M to 5M |
| # of Employees | 35 |
| Plant Area |
18,200
ft2
|
| Annual Production | 125,000
lb
|
| Production Hrs. Annual | 4,420
hrs
|
| Location (State) | Nevada |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $22,442 | 537,808 |
kWh
|
$0.042 |
| Electricity Demand | $21,873 | 2,357 |
kW-mo/yr
|
$9.28 |
| Electricity Fees | $1,498 | - |
|
- |
| Natural Gas | $9,324 | 1,774 |
MMBtu
|
$5.26 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $530,756 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,202 | $4,519 |
$1,217
29,308
kWh
|
$942
-
kW-mo/yr
|
$43 | - | - | - | - | |
| 02 | 2.7231: Use radiant heater for spot heating | $2,445 | $4,015 | - | - | - |
$2,445
-
MMBtu
|
- | - | - | |
| 03 | 2.7243: Improve air circulation with destratification fans / other methods | $1,829 | $800 |
$(-70.0)
(-1,758)
kWh
|
$(-31.0)
-
kW-mo/yr
|
$(-2.0) |
$1,932
-
MMBtu
|
- | - | - | |
| 04 | 3.4116: Meter recycled water (to reduce sewer charges) | $331 | $170 | - | - | - | - |
$331
-
Tgal
|
- | - | |
| 05 | 4.131: Modify process to reduce material use/cost | $500,000 | $3,070,000 | - | - | - | - | - | - | $500,000 | |
| 06 | 4.652: Replace existing equipment with more suitable substitutes | $23,949 | $164,000 | - | - | - | - | - | $3,949 | $20,000 | |
| TOTAL RECOMMENDED | $530,756 | $3,243,504 |
$1,147
27,550
kWh
|
$911
-
kW-mo/yr
|
$41 |
$4,377
-
MMBtu
|
$331
-
Tgal
|
$3,949 | $520,000 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs