ITAC Assessment: NV0116
ITAC logo
ITAC Assessment: NV0116
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Structural Wood Members
NAICS
n/a
SIC 2439: Structural Wood Members, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 70
Plant Area 29,500
ft2
Annual Production 5,000,000
pieces
Production Hrs. Annual 4,485
hrs
Location (State) Nevada

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $12,431 297,773
kWh
Electricity Demand $8,892 958
kW-mo/yr
Electricity Fees $607 -
Natural Gas $2,723 403
MMBtu
Fuel Oil #2 $64,127 6,860
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,634 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $931

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $123 - $78
1,758
kWh
$45
-
kW-mo/yr
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $808 $200 $204
4,982
kWh
$604
-
kW-mo/yr
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,657 $12,973 $1,925
46,014
kWh
$732
-
kW-mo/yr
- -
04 2.8114: Change rate schedules or other changes in utility service $11,871 $50,000 - - - $11,871
05 3.5315: Lease / purchase baler; sell cardboard to recycler $175 - - - $175
-
lb
-
TOTAL RECOMMENDED $15,634 $63,173 $2,207
52,754
kWh
$1,381
-
kW-mo/yr
$175
-
lb
$11,871
TOTAL IMPLEMENTED $931 $200 $282
6,740
kWh
$649
-
kW-mo/yr
- -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs