Assessment Year | 1998 |
---|---|
Principal Product | Ready Mix Concrete |
NAICS |
n/a
|
SIC | 3273: Ready-Mixed Concrete |
Sales Range | $10 M to 50M |
# of Employees | 57 |
Plant Area |
n/a
|
Annual Production | 164,863
units
|
Production Hrs. Annual | 3,588
hrs
|
Location (State) | Nevada |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $13,494 | 182,591 |
kWh
|
$0.074 |
Electricity Demand | $12,212 | 1,316 |
kW-mo/yr
|
$9.28 |
Electricity Fees | $1,236 | - |
|
- |
Natural Gas | $9,873 | 1,880 |
MMBtu
|
$5.25 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $25,654 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1213: Direct warmest air to combustion intake | $346 | $133 | n/a | - | - | - |
$346
-
MMBtu
|
- | - | - | - |
02 | 2.1224: Replace boiler | $3,636 | $17,539 | n/a | - | - | - |
$3,636
-
MMBtu
|
- | - | - | - |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $450 | $1,239 | n/a |
$210
4,689
kWh
|
$231
-
kW-mo/yr
|
$9 | - | - | - | - | - |
04 | 2.4133: Use most efficient type of electric motors | $721 | $2,864 | n/a |
$349
6,448
kWh
|
$358
-
kW-mo/yr
|
$14 | - | - | - | - | - |
05 | 4.441: Install automatic packing equipment | $6,200 | $140 | n/a | - | - | - | - | - | $1,872 | $4,328 | - |
06 | 3.4154: Eliminate leaks in water lines and valves | $877 | $100 | n/a | - | - | - | - |
$877
-
Tgal
|
- | - | - |
07 | 3.4156: Use flow control valves on equipment to optimize water use | $3,073 | $193 | n/a | - | - | - | - |
$3,073
-
Tgal
|
- | - | - |
08 | 3.5311: Recover and reuse waste material | $10,351 | $1,000 | n/a | - | - | - | - |
$2,555
-
Tgal
|
$30,240 | - | $(-22,444.0) |
TOTAL RECOMMENDED | $25,654 | $23,208 |
$559
11,137
kWh
|
$589
-
kW-mo/yr
|
$23 |
$3,982
-
MMBtu
|
$6,505
-
Tgal
|
$32,112 | $4,328 | $(-22,444.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs