ITAC Assessment: NV0110
ITAC logo
ITAC Assessment: NV0110
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Ready Mix Concrete
NAICS
n/a
SIC 3273: Ready-Mixed Concrete
Sales Range $10
M
to 50
M
# of Employees 57
Plant Area
n/a
Annual Production 164,863
units
Production Hrs. Annual 3,588
hrs
Location (State) Nevada

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $13,494 182,591
kWh
Electricity Demand $12,212 1,316
kW-mo/yr
Electricity Fees $1,236 -
Natural Gas $9,873 1,880
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $25,654 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 2.1213: Direct warmest air to combustion intake $346 $133 n/a - - - $346
-
MMBtu
- - - -
02 2.1224: Replace boiler $3,636 $17,539 n/a - - - $3,636
-
MMBtu
- - - -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $450 $1,239 n/a $210
4,689
kWh
$231
-
kW-mo/yr
$9 - - - - -
04 2.4133: Use most efficient type of electric motors $721 $2,864 n/a $349
6,448
kWh
$358
-
kW-mo/yr
$14 - - - - -
05 4.441: Install automatic packing equipment $6,200 $140 n/a - - - - - $1,872 $4,328 -
06 3.4154: Eliminate leaks in water lines and valves $877 $100 n/a - - - - $877
-
Tgal
- - -
07 3.4156: Use flow control valves on equipment to optimize water use $3,073 $193 n/a - - - - $3,073
-
Tgal
- - -
08 3.5311: Recover and reuse waste material $10,351 $1,000 n/a - - - - $2,555
-
Tgal
$30,240 - $(-22,444.0)
TOTAL RECOMMENDED $25,654 $23,208 $559
11,137
kWh
$589
-
kW-mo/yr
$23 $3,982
-
MMBtu
$6,505
-
Tgal
$32,112 $4,328 $(-22,444.0)
TOTAL IMPLEMENTED - - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs