| Assessment Year | 1998 |
|---|---|
| Principal Product | Pipe, Concrete |
| NAICS |
n/a
|
| SIC | 3272: Concrete Products, Except Block and Brick |
| Sales Range | $1 M to 5M |
| # of Employees | 20 |
| Plant Area |
18,400
ft2
|
| Annual Production | 38,000
ton
|
| Production Hrs. Annual | 2,730
hrs
|
| Location (State) | Nevada |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $16,914 | 338,804 |
kWh
|
$0.050 |
| Electricity Demand | $10,568 | 2,118 |
kW-mo/yr
|
$4.99 |
| Electricity Fees | $2,422 | - |
|
- |
| Natural Gas | $13,362 | 2,486 |
MMBtu
|
$5.37 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $135,464 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $29,220 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Product Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7134: Use photocell controls | $1,515 | $340 |
$936
18,757
kWh
|
$549
-
kW-mo/yr
|
$30 | - | - | - | - | - | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $995 | $950 |
$639
12,896
kWh
|
$336
-
kW-mo/yr
|
$20 | - | - | - | - | - | |
| 03 | 2.4314: Use synthetic lubricant | $3,450 | $800 |
$2,214
44,549
kWh
|
$1,168
-
kW-mo/yr
|
$68 | - | - | - | - | - | |
| 04 | 2.8113: Purchase gas directly from a contract gas supplier | $1,336 | $750 | - | - | - | - | - | $1,336 | - | - | |
| 05 | 4.112: Replace old machine with new automatic multi-station tool | $99,943 | $575,000 | - | - | - |
$3,608
-
MMBtu
|
- | - | - | $96,335 | |
| 06 | 4.112: Replace old machine with new automatic multi-station tool | $28,225 | $116,750 | - | - | - | - |
$4,212
-
lb
|
- | $24,013 | - | |
| TOTAL RECOMMENDED | $135,464 | $694,590 |
$3,789
76,202
kWh
|
$2,053
-
kW-mo/yr
|
$118 |
$3,608
-
MMBtu
|
$4,212
-
lb
|
$1,336 | $24,013 | $96,335 | ||
| TOTAL IMPLEMENTED | $29,220 | $117,700 |
$639
12,896
kWh
|
$336
-
kW-mo/yr
|
$20 | - |
$4,212
-
lb
|
- | $24,013 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Product Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs