| Assessment Year | 1997 |
|---|---|
| Principal Product | Western Jewelry |
| NAICS |
n/a
|
| SIC | 3961: Costume Jewelry and Costume Novelties, Except Precious Metal |
| Sales Range | $5 M to 10M |
| # of Employees | 60 |
| Plant Area |
15,000
ft2
|
| Annual Production | 195,000
pieces
|
| Production Hrs. Annual | 2,184
hrs
|
| Location (State) | Nevada |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $40,079 | 916,471 |
kWh
|
$0.044 |
| Electricity Demand | $31,301 | 3,373 |
kW-mo/yr
|
$9.28 |
| Electricity Fees | $339 | - |
|
- |
| Natural Gas | $24,854 | 4,787 |
MMBtu
|
$5.19 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $72,219 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,198 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,055 | $232 |
$487
11,137
kWh
|
$568
-
kW-mo/yr
|
- | - | |
| 02 | 2.7111: Reduce illumination to minimum necessary levels | $761 | $125 |
$351
7,913
kWh
|
$410
-
kW-mo/yr
|
- | - | |
| 03 | 2.7135: Install occupancy sensors | $135 | $163 |
$71
1,758
kWh
|
$64
-
kW-mo/yr
|
- | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $122 | $200 |
$122
2,931
kWh
|
- | - | - | |
| 05 | 2.4133: Use most efficient type of electric motors | $340 | $592 |
$274
6,155
kWh
|
$66
-
kW-mo/yr
|
- | - | |
| 06 | 2.2511: Insulate bare equipment | $1,179 | $1,154 |
$1,179
14,947
kWh
|
- | - | - | |
| 07 | 2.2514: Cover open tanks | $897 | $375 |
$444
10,258
kWh
|
$453
-
kW-mo/yr
|
- | - | |
| 08 | 4.425: Eliminate/reduce redundant inspections | $66,700 | $25,000 | - | - | $66,700 | - | |
| 09 | 4.821: Pay bills on time to avoid late fees | $1,030 | - | - | - | - | $1,030 | |
| TOTAL RECOMMENDED | $72,219 | $27,841 |
$2,928
55,099
kWh
|
$1,561
-
kW-mo/yr
|
$66,700 | $1,030 | ||
| TOTAL IMPLEMENTED | $2,198 | $1,729 |
$1,745
28,136
kWh
|
$453
-
kW-mo/yr
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs