Assessment Year | 1997 |
---|---|
Principal Product | Aftermarket and OEM vehicle fuel tanks |
NAICS |
n/a
|
SIC | 3417: |
Sales Range | $1 M to 5M |
# of Employees | 37 |
Plant Area |
30,000
ft2
|
Annual Production | 1,090,000
lb
|
Production Hrs. Annual | 2,210
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $25,091 | 297,773 |
kWh
|
$0.084 |
Electricity Demand | $5,238 | 1,387 |
kW-mo/yr
|
$3.78 |
Electricity Fees | $2,522 | - |
|
- |
Natural Gas | $7,762 | 1,331 |
MMBtu
|
$5.83 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $19,489 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,761 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2525: Eliminate cooling of process streams which subsequently must be heated and vice versa | $1,252 | $200 | - | - |
$1,252
-
MMBtu
|
- | - | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $728 | $50 |
$608
7,327
kWh
|
$120
-
kW-mo/yr
|
- | - | - | |
03 | 2.7124: Make a practice of turning off lights when not needed | $1,478 | $125 |
$762
9,086
kWh
|
$716
-
kW-mo/yr
|
- | - | - | |
04 | 2.1135: Repair furnaces and oven doors so that they seal efficiently | $729 | $100 | - | - |
$729
-
MMBtu
|
- | - | |
05 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $336 | $100 | - | - | - |
$336
-
lb
|
- | |
06 | 4.425: Eliminate/reduce redundant inspections | $14,966 | $7,500 | - | - | - | - | $14,966 | |
TOTAL RECOMMENDED | $19,489 | $8,075 |
$1,370
16,413
kWh
|
$836
-
kW-mo/yr
|
$1,981
-
MMBtu
|
$336
-
lb
|
$14,966 | ||
TOTAL IMPLEMENTED | $18,761 | $8,025 |
$762
9,086
kWh
|
$716
-
kW-mo/yr
|
$1,981
-
MMBtu
|
$336
-
lb
|
$14,966 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs