Assessment Year | 1997 |
---|---|
Principal Product | Pressure treated wood products |
NAICS |
n/a
|
SIC | 2491: Wood Preserving |
Sales Range | $1 M to 5M |
# of Employees | 26 |
Plant Area |
350,000
ft2
|
Annual Production | 1,500,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Nevada |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $29,012 | 623,388 |
kWh
|
$0.047 |
Electricity Demand | $15,516 | 1,687 |
kW-mo/yr
|
$9.20 |
Electricity Fees | $1,349 | - |
|
- |
Natural Gas | $88,638 | 16,938 |
MMBtu
|
$5.23 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $31,508 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,533 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $8,890 | $9,124 | - | - |
$8,890
-
MMBtu
|
- | - | |
02 | 2.2511: Insulate bare equipment | $13,870 | $7,320 | - | - |
$13,870
-
MMBtu
|
- | - | |
03 | 2.2135: Repair and eliminate steam leaks | $1,071 | $250 | - | - |
$1,071
-
MMBtu
|
- | - | |
04 | 2.2511: Insulate bare equipment | $325 | $409 | - | - |
$325
-
MMBtu
|
- | - | |
05 | 2.7135: Install occupancy sensors | $896 | $196 |
$737
15,826
kWh
|
$159
-
kW-mo/yr
|
- | - | - | |
06 | 2.2437: Recover waste heat from equipment | $3,129 | $3,350 | - | - |
$3,129
-
MMBtu
|
- | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $137 | $10 |
$137
2,931
kWh
|
- | - | - | - | |
08 | 3.3128: Utilize other methods to remove contaminants | $840 | $408 | - | - | - |
$840
-
lb
|
- | |
09 | 4.821: Pay bills on time to avoid late fees | $2,350 | - | - | - | - | - | $2,350 | |
TOTAL RECOMMENDED | $31,508 | $21,067 |
$874
18,757
kWh
|
$159
-
kW-mo/yr
|
$27,285
-
MMBtu
|
$840
-
lb
|
$2,350 | ||
TOTAL IMPLEMENTED | $1,533 | $669 |
$137
2,931
kWh
|
- |
$1,396
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs