ITAC Assessment: NV0076
ITAC logo
ITAC Assessment: NV0076
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Steel Reloading Dies
NAICS
n/a
SIC 3559: Special Industry Machinery, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 105,000
ft2
Annual Production 700,000
pieces
Production Hrs. Annual 3,744
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $211,862 2,487,104
kWh
Electricity Demand $33,666 7,904
kW-mo/yr
Electricity Fees $12,678 -
Natural Gas $34,095 6,393
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $57,465 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,295

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings
01 2.4133: Use most efficient type of electric motors $134 $37 $117
10,844
kWh
$17
-
kW-mo/yr
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,161 $300 $1,161
13,775
kWh
- - -
03 2.7135: Install occupancy sensors $729 $327 $649
7,620
kWh
$80
-
kW-mo/yr
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $9,956 $1,911 $8,581
100,821
kWh
$1,375
-
kW-mo/yr
- -
05 2.7111: Reduce illumination to minimum necessary levels $5,980 $800 $5,180
60,961
kWh
$800
-
kW-mo/yr
- -
06 2.2437: Recover waste heat from equipment $7,229 $4,000 - - $7,229
-
MMBtu
-
07 3.8141: Regenerate cleaning solvent on-site and reuse $30,371 $47,825 - - - $30,371
-
gal
08 3.4155: Meter waste water $1,905 $4,000 - - - $1,905
-
gal
TOTAL RECOMMENDED $57,465 $59,200 $15,688
194,021
kWh
$2,272
-
kW-mo/yr
$7,229
-
MMBtu
$32,276
-
gal
TOTAL IMPLEMENTED $1,295 $337 $1,278
24,619
kWh
$17
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs