| Assessment Year | 1996 |
|---|---|
| Principal Product | Rotary Cutting Tools |
| NAICS |
n/a
|
| SIC | 3541: Machine Tools, Metal Cutting Types |
| Sales Range | $5 M to 10M |
| # of Employees | 70 |
| Plant Area |
42,500
ft2
|
| Annual Production | 325,000
lb
|
| Production Hrs. Annual | 5,460
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $91,659 | 1,044,256 |
kWh
|
$0.088 |
| Electricity Demand | $13,918 | 3,005 |
kW-mo/yr
|
$4.63 |
| Electricity Fees | $1,255 | - |
|
- |
| Natural Gas | $993 | 149 |
MMBtu
|
$6.66 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $18,994 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $13,594 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Liquid (non-haz) Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $6,386 | $20 |
$5,829
66,530
kWh
|
$557
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $743 | $200 |
$743
8,499
kWh
|
- | - | - | - | |
| 03 | 2.7111: Reduce illumination to minimum necessary levels | $413 | - |
$374
4,396
kWh
|
$39
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.7135: Install occupancy sensors | $968 | $282 |
$868
9,965
kWh
|
$100
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,846 | $920 | - | - | - | - | $1,846 | |
| 06 | 2.4323: Use optimum size and capacity equipment | $3,238 | $180 | - | - | $3,238 | - | - | |
| 07 | 3.7393: Implement a machine and coolant sump cleaning program to minimize coolant contamination | $5,400 | $10,000 | - | - | - |
$5,400
-
gal
|
- | |
| TOTAL RECOMMENDED | $18,994 | $11,602 |
$7,814
89,390
kWh
|
$696
-
kW-mo/yr
|
$3,238 |
$5,400
-
gal
|
$1,846 | ||
| TOTAL IMPLEMENTED | $13,594 | $1,602 |
$7,814
89,390
kWh
|
$696
-
kW-mo/yr
|
$3,238 | - | $1,846 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Liquid (non-haz) Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs