| Assessment Year | 1996 |
|---|---|
| Principal Product | Liquified Gas Pumps |
| NAICS |
n/a
|
| SIC | 3568: Mechanical Power Transmission Equipment, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 65 |
| Plant Area |
30,000
ft2
|
| Annual Production | 175
pieces
|
| Production Hrs. Annual | 2,527
hrs
|
| Location (State) | Nevada |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $25,459 | 591,149 |
kWh
|
$0.043 |
| Electricity Demand | $53,831 | 6,857 |
kW-mo/yr
|
$7.85 |
| Electricity Fees | $5,780 | - |
|
- |
| Natural Gas | $11,928 | 2,279 |
MMBtu
|
$5.23 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $15,304 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $12,604 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $879 | $2,000 |
$284
6,448
kWh
|
$566
-
kW-mo/yr
|
$29 | - | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $65 | $18 |
$65
1,465
kWh
|
- | - | - | - | |
| 03 | 2.7111: Reduce illumination to minimum necessary levels | $1,095 | $30 |
$566
13,189
kWh
|
$471
-
kW-mo/yr
|
$58 | - | - | |
| 04 | 2.7135: Install occupancy sensors | $570 | $144 |
$258
5,862
kWh
|
$283
-
kW-mo/yr
|
$29 | - | - | |
| 05 | 2.3212: Optimize plant power factor | $245 | $600 | - | - | $245 | - | - | |
| 06 | 2.2511: Insulate bare equipment | $9,750 | $268 | - | - | - |
$9,750
-
Tgal
|
- | |
| 07 | 3.6125: Sell combustible waste | $2,700 | $5,000 | - | - | - | - |
$2,700
-
lb
|
|
| TOTAL RECOMMENDED | $15,304 | $8,060 |
$1,173
26,964
kWh
|
$1,320
-
kW-mo/yr
|
$361 |
$9,750
-
Tgal
|
$2,700
-
lb
|
||
| TOTAL IMPLEMENTED | $12,604 | $3,060 |
$1,173
26,964
kWh
|
$1,320
-
kW-mo/yr
|
$361 |
$9,750
-
Tgal
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs