Assessment Year | 1996 |
---|---|
Principal Product | recreational motor homes |
NAICS |
n/a
|
SIC | 3716: Motor Homes |
Sales Range | $100 M to 500M |
# of Employees | 325 |
Plant Area |
120,000
ft2
|
Annual Production | 2,500
pieces
|
Production Hrs. Annual | 2,431
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $135,691 | 1,735,639 |
kWh
|
$0.078 |
Electricity Demand | $85,483 | 6,646 |
kW-mo/yr
|
$12.86 |
Electricity Fees | $2,100 | - |
|
- |
Natural Gas | $43,480 | 6,016 |
MMBtu
|
$7.23 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $21,706 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $20,159 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $469 | $81 |
$248
3,224
kWh
|
$221
-
kW-mo/yr
|
- | - | |
02 | 2.7243: Improve air circulation with destratification fans / other methods | $727 | $1,625 | - | - |
$727
-
MMBtu
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $930 | $300 |
$930
12,016
kWh
|
- | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $820 | - |
$820
10,551
kWh
|
- | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $185 | - |
$103
1,465
kWh
|
$82
-
kW-mo/yr
|
- | - | |
06 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $18,575 | $17,350 | - | - | - |
$18,575
-
lb
|
|
TOTAL RECOMMENDED | $21,706 | $19,356 |
$2,101
27,256
kWh
|
$303
-
kW-mo/yr
|
$727
-
MMBtu
|
$18,575
-
lb
|
||
TOTAL IMPLEMENTED | $20,159 | $17,731 |
$1,281
16,705
kWh
|
$303
-
kW-mo/yr
|
- |
$18,575
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs